CEZ submitted an application for a new permit to operate Unit 1 of the Temelín Nuclear Power Plant

On Wednesday, March 25, 2020, ČEZ, a. s. submitted an application for the permit to operate the Unit 1 of the Temelín Nuclear Power Plant to the State Office for Nuclear Safety (SÚJB).

The existing permit for operation remains valid until the new permit come in force. The period for administrative procedure is set within the 6 months from application delivery, in accordance with the provisions of article 19 para. 2 letter d) of Act No. 263/2016 Coll., the Atomic Act. 

SÚJB decision will be based on the results of the detailed review of the application and submitted documentation for the permitted activity required by the Appendix 1 letter f) of the Atomic Act. Results of the periodic safety review will be also considered. SÚJB inspectors and experts of the specialized technical support organization SÚRO, v.v.i. will be involved in the review process.